Secondary 2 · Technology
The technology project · The technology project

Project Documentation

Before you start, make sure you know: The phases of a technology project (Secondary Year 1)
Before you start, make sure you know: Sketches, rough drawings, and views (Secondary Year 1)

At your school there's a problem: sweaters and backpacks end up on the floor because there's nowhere to hang them. Your team builds a coat rack and it works. But a year later another group wants to build one too, and nobody remembers the measurements or how much it cost. What should have been saved so they could build it without guessing? That is what documenting a project means.

The documents of a project

A technology project starts from a problem identified at school or in the community. You take into account the criteria and conditions of the place: what materials are available, how much money can be spent, how much time you have, and who is going to use it. Five documents keep everything you need to know, from the idea all the way to the accounts.

The five documents of a project, illustrated with the example of a coat rack: the report with text and images, the dimensioned drawings, the bill of materials with quantities, the Gantt chart for planning, and the budget with its total. 60 cm × 1 × 3 × 6 $120 $40 $30 Total $190 report drawings bill of materials planning budget

Sketch and drawing

The sketch (or rough draft) is a quick freehand drawing for thinking: you try out ideas, make corrections, and discard options without wasting material. The drawing (or plan) is the exact, dimensioned drawing used to build. A sketch without measurements is no good for cutting; the drawing can't exist without first thinking things through with sketches. That's why you need both.

When the project is mass-produced

If a company were going to make 500 coat racks, the folder would have to be more demanding, because nobody can ask you "what did you mean by this?" Here are the differences compared with a school project:

  • Drawings with tolerances. Tolerance is the allowed variation in a measurement, for example 60 cm ± 1 mm. This way, pieces made by different machines or people fit together, and fewer pieces are rejected.

  • Materials with commercial references. Instead of "a pine board," you write down the type, thickness, size, and the supplier or code. That way you always buy the same thing and can order it in large quantities at a better price.

  • Cost per unit calculated over the whole production run. All the costs (materials, labor, tools) are added up and divided by the number of pieces. If the mold or template costs $\$2{,}000$ and 500 pieces are made, it adds $2000 \div 500 = \$4$ to each one; if only 10 were made, it would be $\$200$ per piece. The more pieces you make, the less each fixed cost weighs.

Each requirement makes manufacturing cheaper because it prevents errors, waste, and lost time, and because it makes it possible to buy and produce in bulk.

Practice★☆☆Not started
List the five basic documents of a technology project (report, drawings, list of materials, planning schedule, and budget) and write a sentence explaining what each…

List the five basic documents of a technology project (report, drawings, list of materials, planning schedule, and budget) and write a sentence explaining what each contributes and who would need it.

Solve
Practice★☆☆Not started
Match each document to its content and justify one of the pairs: (a) report: justified account of the whole process; (b) drawings: technical drawings with the…

Match each document to its content and justify one of the pairs: (a) report: justified account of the whole process; (b) drawings: technical drawings with the measurements of the object; (c) list of materials: everything needed, with quantities; (d) budget: itemised costs and their total. Which document would you consult first if you wanted to repeat the project?

Solve
Practice★☆☆Not started
Explain the difference between a rough sketch or draft (a quick freehand drawing for brainstorming) and a final technical drawing (an exact, dimensioned drawing for…

Explain the difference between a rough sketch or draft (a quick freehand drawing for brainstorming) and a final technical drawing (an exact, dimensioned drawing for manufacturing), and explain why both are necessary and neither can replace the other.

Solve
Practice★☆☆Not started
A classmate wants to repeat your project from last year using only your document folder. Explain which documents they will review and in what order, and what will happen…

A classmate wants to repeat your project from last year using only your document folder. Explain which documents they will review and in what order, and what will happen if any of them is missing.

Solve
Practice★★★Not started
An industrial workshop agrees to manufacture a pre-series of 500 coat racks based on your classroom prototype, but returns the technical dossier stating that mass…

An industrial workshop agrees to manufacture a pre-series of 500 coat racks based on your classroom prototype, but returns the technical dossier stating that mass production is unfeasible with that documentation. They point out three deficiencies:

  1. a) The drawings have nominal dimensions without dimensional tolerances ($\pm 0.5\ \text{mm}$).
  2. b) The bill of materials generically indicates "wood and screws", without standardized commercial references or finishes.
  3. c) The budget charges the entire cost of special tools to a single unit instead of apportioning it.

Explain what extra costs and assembly line failures each of these three omissions would cause, and write a corrected example for each case as required by a technical office.

Solve

The report: telling the process in an orderly way

The project report is not just a description of the object: it is the justified story of the decisions that were made.

The goal must answer four things: what problem it solves, for whom, with what limitations (of materials, time, or money), and how you will know it works.

The five parts of the report in order: goal, design, construction, budget, and conclusions, connected by arrows. 1. Goal 2. Design 3. Construc- tion 4. Bud- get 5. Conclu- sions what problem? why this one? how was it made? how much did it cost? what did we learn?
Practice★☆☆Not started
Order the parts of a project report and explain what each one describes in one sentence: conclusions and difficulties, project objective, chosen design, construction…

Order the parts of a project report and explain what each one describes in one sentence: conclusions and difficulties, project objective, chosen design, construction process, final budget.

Solve
Practice★★☆Not started
Write the 'objective' section of the report for a specific project: an adjustable tablet stand made from recycled materials. Write between four and six lines addressing…

Write the 'objective' section of the report for a specific project: an adjustable tablet stand made from recycled materials. Write between four and six lines addressing what problem it solves, for whom, under what material constraints, and how it will be known to work.

Solve
Practice★★★Not started
During the stress test of a toothpick bridge with a $40\ \text{cm}$ span, the structure fails at $18\ \text{N}$ (approx. $1.8\ \text{kg}$). After the test in the…

During the stress test of a toothpick bridge with a $40\ \text{cm}$ span, the structure fails at $18\ \text{N}$ (approx. $1.8\ \text{kg}$). After the test in the workshop, two technical facts are confirmed:

  1. The wooden members did not fracture, but the joints of the lower nodes detached cleanly, revealing glue applied in a thick layer without clamping, tested after $12\ \text{h}$ of drying instead of the recommended $24\ \text{h}$.

  2. The upper truss suffered lateral buckling (it bowed to one side) seconds before the collapse of the nodes.

Write the "Incidents, failure analysis, and improvements" section of the technical report: determine the physical or process cause of each problem using structural technical terminology, and detail two specific modifications (one design-related and one manufacturing-related) for version 2.0.

Solve
Practice★★★Not started
A 3rd-year ESO group receives the technical dossier from the previous year to build an exact duplicate of a programmed traffic light with electronic control. The folder…

A 3rd-year ESO group receives the technical dossier from the previous year to build an exact duplicate of a programmed traffic light with electronic control. The folder only contains the program code, a photo of the finished prototype, and the overall budget of expenses. When attempting to manufacture it in the workshop, three problems arise:

  1. The LED diodes burn out when connected to the power supply because the value of the associated resistors is not listed.

  2. The 3D-printed enclosure does not close because the screw holes do not align with the perforated board.

  3. When soldering the components, the printed circuit board traces deteriorate due to applying heat in the wrong order.

Indicate which specific technical document was missing from the dossier for each of the three problems, what standardized data each document should have contained, and draft the circuit's process sheet with precise instructions to avoid soldering damage.

Solve

Planning: the Gantt chart

Spreading tasks out over time keeps you from running late and lets you see at a glance whether the project is behind schedule. Planning means deciding which actions, which technical means (tools, workshop), and which supplies (materials) are needed, and when.

Gantt chart with four tasks in rows and time in columns: design, shopping, construction, and testing; the testing overlaps with the end of construction. Week 1 Week 2 Week 3 Week 4 design shopping construction testing testing overlaps with the end of construction

Two rules for putting together a Gantt chart:

  • A task that needs the result of another one goes after it (you don't build without drawings).

  • Independent tasks can overlap (you buy the wood while you decide on the hardware).

If the workshop is available only a few hours, tasks that don't need it (design, report, shopping) are done outside it.

Practice★☆☆Not started
The figure shows the planning of a six-week project using a Gantt chart: each row is a task and each column is a week. Between construction and presentation there is a…

The figure shows the planning of a six-week project using a Gantt chart: each row is a task and each column is a week.

W1 W2 W3 W4 W5 W6 Design and drawings Purchasing materials Construction ? ? Presentation

Between construction and presentation there is a covered task occupying weeks 5 and 6: testing the object and correcting any errors that appear. Explain what is done in this task, why it is useful for it to overlap slightly with construction, and the risk of planning without allocating time for it.

Solve
Practice★☆☆Not started
Explain what a Gantt chart is: what each row and column represents, what it means when two bars overlap in time, and why it helps to know if a project is running behind…

Explain what a Gantt chart is: what each row and column represents, what it means when two bars overlap in time, and why it helps to know if a project is running behind schedule just by looking at it.

Solve
Practice★★☆Not started
In project planning, the task 'purchasing materials' overlaps with 'finishing the drawings'. Explain why this overlap makes sense (timber can be bought while deciding on…

In project planning, the task 'purchasing materials' overlaps with 'finishing the drawings'. Explain why this overlap makes sense (timber can be bought while deciding on the hardware), which task should never overlap with construction, and what happens if two interdependent tasks are planned in reverse order.

Solve
Practice★★☆Not started
Your class is organising an end-of-term party over four weeks. Create a schedule with five tasks (choosing activities, budgeting, purchasing, preparing the venue,…

Your class is organising an end-of-term party over four weeks. Create a schedule with five tasks (choosing activities, budgeting, purchasing, preparing the venue, party), assign them weeks using a Gantt chart described in text, and justify which tasks can overlap and which cannot.

Solve
Practice★★☆Not started
A project must be completed in six weeks and the workshop is only available for two hours per week. Explain how this restriction conditions the planning (what tasks can…

A project must be completed in six weeks and the workshop is only available for two hours per week. Explain how this restriction conditions the planning (what tasks can be done outside the workshop: design, report, purchasing) and how you would show this on a Gantt chart.

Solve
Practice★★★Not started
Analyze the following schedule proposed by a 3rd-year ESO team to build an electromechanical prototype in 6 weeks (12 workshop sessions): | Task | Wk 1 | Wk 2 | Wk 3 |…

Analyze the following schedule proposed by a 3rd-year ESO team to build an electromechanical prototype in 6 weeks (12 workshop sessions):

Task Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6
A. Purchase of materials and components [X]
B. Preliminary design and dimensioned drawings [X] [X]
C. Layout, cutting, and machining [X]
D. Electrical and structural assembly [X]
E. Operating tests and final report [X]

Identify three methodological flaws in precedence and risk management in this chart. Justify the practical consequences that the team will suffer in the workshop with this distribution, and develop a corrected version in a table, justifying the overlaps between phases.

Solve
Practice★★★Not started
Two team members (Operator A and Operator B) must manufacture an articulated support in 4 workshop sessions of 2 hours each (8 hours in total). The required tasks are:…

Two team members (Operator A and Operator B) must manufacture an articulated support in 4 workshop sessions of 2 hours each (8 hours in total). The required tasks are:

  • Task 1: Marking out and cutting profiles (2 h, 1 operator).

  • Task 2: Drilling and deburring (2 h, requires Task 1, 1 operator).

  • Task 3: Sanding and anti-rust treatment (2 h, requires Task 2, 1 operator).

  • Task 4: Assembly and riveting of the structure (2 h, requires Task 2 and strictly requires both operators at the same time for safety reasons).

  • Task 5: Mechanical tests and final adjustments (2 h, requires Task 3 and Task 4, 2 operators).

Demonstrate by means of a session-by-session assignment table whether it is possible to finish within the 4 planned sessions without violating dependencies or safety rules. Identify the critical path and propose what reorganization or splitting of tasks would make it possible to avoid idle times for stopped operators.

Solve

The bill of materials and the budget

The budget answers a concrete question: how much is this project going to cost? Prices are checked at the hardware store, the lumberyard, or the street market, and it pays to compare.

Budget for a coat rack: bars proportional to the cost of each item (boards 160 pesos, screws 40 pesos, varnish 35 pesos) and a total of 235 pesos. 2 boards × 80 pesos 160 pesos 1 box of screws 40 pesos ½ can of varnish 35 pesos 160 + 40 + 35 total = 235 pesos

A complete bill of materials also includes a line for necessary tools (saw, screwdriver, tape measure). They aren't bought, but they limit the project: if one is missing and it's expensive, the cost can double.

Practice★☆☆Not started
A list of materials is used for buying items without forgetting anything or having leftovers. State the minimum four pieces of information each line must have (item…

A list of materials is used for buying items without forgetting anything or having leftovers. State the minimum four pieces of information each line must have (item name, quantity, specification or measurement, unit price) and write three example lines for a wooden coat rack.

Solve
Practice★★☆Not started
Complete the budget for a wooden laptop stand: (a) two pine boards at $\$160$ each; (b) a box of screws at $\$80$; (c) half a tin of varnish if a whole tin costs…

Complete the budget for a wooden laptop stand: (a) two pine boards at $\$160$ each; (b) a box of screws at $\$80$; (c) half a tin of varnish if a whole tin costs $\$140$; (d) four rubber feet at $\$10$ each. Calculate the subtotal for each item and the total, and explain why 'a box of screws' appears in the list even if you only use eight.

Solve
Practice★★☆Not started
The chart shows the breakdown of the budget for a plant trolley, with the total covered. Calculate the total budget, state which item accounts for the largest share, and…

The chart shows the breakdown of the budget for a plant trolley, with the total covered.

Treated timber $18 Wheels $12 Hardware and screws $9 Paint $6 total = ?

Calculate the total budget, state which item accounts for the largest share, and propose two specific changes that would lower the budget without ruining the project, explaining how much each would save.

Solve
Practice★★☆Not started
A budget overlooks two things: VAT on materials and the tools that will need to be bought. Explain how each oversight disrupts the budget (one inflates all items by a…

A budget overlooks two things: VAT on materials and the tools that will need to be bought. Explain how each oversight disrupts the budget (one inflates all items by a percentage; the other can double the cost if an expensive tool is missing) and what 'contingency' item you would include in your budgets.

Solve
Practice★★☆Not started
Describe a simple shelving unit: two side panels of $60\ \text{cm}$, three shelves of $50\ \text{cm}$, twelve screws, glue, and four bracket supports. Write its full…

Describe a simple shelving unit: two side panels of $60\ \text{cm}$, three shelves of $50\ \text{cm}$, twelve screws, glue, and four bracket supports. Write its full list of materials with quantities and specifications, and add a line for 'tools required', which are not purchased but condition the project.

Solve
Practice★★★Not started
You must prepare a comparative budget to build 10 nest boxes in the workshop. Option A uses new plywood boards: material cost of $\$24…

You must prepare a comparative budget to build 10 nest boxes in the workshop. Option A uses new plywood boards: material cost of $\$24$, estimated manufacturing time of $10\ \text{h}$, and a $5\ \%$ scrap rate (cutting waste). Option B reuses pallet wood: material cost of $\$0$, but requires $\$8$ in water-based fungicide treatments, specific screws for $\$6$, a working time of $22\ \text{h}$ (dismantling, de-nailing, sanding), and a $25\ \%$ scrap rate due to cracked boards. If labor is valued at $5\ \text{\$/h}$ and a $10\ \%$ contingency is added to the accumulated total cost of each alternative: calculate the unit cost per box for each option and technically justify which one you should choose if the workshop only has 14 class hours available for the entire term.

Solve
Practice★★★Not started
A 3rd-year ESO school cooperative manufactures wooden phone stands and decides to sell them at $\$12$ per unit, estimating that it spends $\$5$ on wood and screws per…

A 3rd-year ESO school cooperative manufactures wooden phone stands and decides to sell them at $\$12$ per unit, estimating that it spends $\$5$ on wood and screws per stand and that the remaining $\$7$ is pure profit. Upon reviewing the figures, they discover losses. Analyze the mistake based on these real unallocated costs:

  • Labor: $45\ \text{min}$ per piece at a rate of $8\ \text{\$/h}$.

  • Overhead costs (wear of drill bits, sandpaper, glue, and electricity): $\$1.20$ per piece.

  • Scrap due to defective parts: an additional $10\ \%$ on direct manufacturing costs (materials and labor).

  • Taxes: $21\ \%$ VAT on the final selling price.

Calculate the real unit production cost, determine how much money they were losing on each stand sold at $\$12$, and set the new retail price (RRP) that guarantees a net profit of $15\ \%$ before taxes.

Solve

Consistency across documents

The five documents must tell the same story. If the drawing says the tank is 12 cm tall and the bill of materials buys a bottle that is 8 cm tall, the project fails even though each document is fine on its own.

Before building, check three things:

  • The measurements in the drawing match the materials in the list.

  • Everything that appears in the process (glue, solder, screws) is in the list and in the budget.

  • Each task in the Gantt chart has its materials bought and its tools available before it starts.

Practice★★★Not started
A classroom team presents the preliminary project for a self-watering planter for technical validation. When auditing the folder of project documents, you detect three…

A classroom team presents the preliminary project for a self-watering planter for technical validation. When auditing the folder of project documents, you detect three serious inconsistencies among them:

  1. On the dimensioned part drawing, the inner reservoir has a diameter of $12\ \text{cm}$, but the bill of materials lists a standard $8\ \text{cm}$ bottle.

  2. The budget includes hot-melt adhesive, but the technical process sheet specifies heat-welding the polypropylene parts to ensure watertightness.

  3. In the Gantt chart, the filling and watertightness test is scheduled for the same assembly session, before the sealants have cured.

Explain the real impact that each contradiction would have if moving directly to manufacturing in the workshop, and write down the precise corrections that must be recorded in the technical report.

Solve

Go back to the beginning: for another group to repeat the coat rack without guessing, you have to leave them the report, the dimensioned sketches and drawings, the bill of materials, the Gantt chart, and the budget, all consistent with one another.

Summary